BELOIT — A routine facade restoration project in downtown Beloit has evolved into a nearly year-long intensive rehabilitation, illustrating the unpredictable nature of preserving historic infrastructure. The Hanchett Block building at 307 State St., a site famously visited by Abraham Lincoln in 1859 for an anti-slavery address, has served as the latest test case for Corporate Contractors Inc. (CCI) and Hendricks Commercial Properties (HCP).
What was originally envisioned as a 10-week, $20,000 project to replace windows and modify the facade has ballooned significantly. According to project managers, the initial scope was disrupted almost immediately after crews began peeling back the building’s exterior.
## The Complexity of Historic Restoration
The primary hurdle encountered by construction teams was the discovery of unstable shotcrete behind the building’s exterior masonry. The material, which had been applied to the structure years prior, lacked the integrity required to support the planned “thin-brick” veneer system.
“These older buildings, especially when it’s limestone, you never know what you’re going to get when you start digging into it,” noted Stenson El-Amin, an assistant project manager at CCI. Beyond the crumbling shotcrete, the construction team was forced to reinforce a failing parapet on the south side and install heavy
Disclaimer: This content is auto-generated for informational purposes only.
Source: Read Original News