Due to its protections, construction can only take place during the months of April and October. The team, which includes construction partner Kier, must work around different breeding seasons and create appropriate relocation habitats for wildlife before works can take place. Matt Phillips, senior project manager at Kier, says his team had more ecologists than engineers in the beginning “because we had to learn and understand the habitat”.